Installation planning authority
Prepared and technically reviewed by UJIA
UJIA coordinates kinetic facade interfaces from verified survey data and approved project drawings through setting-out, logistics, access, trial installation, commissioning and handover.
Responsibility and acceptance matrix
- Project design team: building structure, design actions, local approvals and coordinated interfaces.
- UJIA: kinetic components, project-specific product drawings, movement clearances and product inspection criteria within the agreed scope.
- Installer: site verification, approved method statement, setting-out, fastener records, safe access and installation quality.
- Handover evidence: signed inspections, marked-up elevations, representative motion tests, photographs, component IDs and accepted corrective work.
Standards and project controls
Confirm the applicable local code and edition. Wind actions may be developed using ASCE/SEI 7 or EN 1991-1-4; atmospheric exposure may be classified using ISO 9223. These references do not replace approved calculations, local safety requirements or project-specific method statements.
Use the tile installation guide for brackets, pivots and field tolerances, and the maintenance guide for service-life planning.